facebook  google plus  twitter
Coldstream/coldstream_4_1510776451.jpg

Coldstream Lumber - Recover

2014

Coldstream Lumber - Recover

Fabric Building Re and Re
120’ x 140’ with 20' Bay Spacings
  1.      Supply and Install
  2.      Replaced all panels on main cover
  3.      New end wall
  4.      Framed new openings and provided signage
Purpose: Fire Damage Cover Replacement
WilliamsScotsman/ws1_1510776292.jpg

Williams Scotsman

2014

Williams Scotsman

Fabric Building 
32’x 80’ with 8' Bay Spacings and 10' leg
  1.      Supply and Install
  2.      Foundation install with steel plates
  3.      Open concept
Purpose: General storage
linde/linde3_1510776250.jpg

Linde Canada

2014

Linde Canada

Two Steel Buildings
15’x 20’ and 15' x 30'
  1.      Supply and Install
  2.      Fully insulated roof
  3.      HVAC and AC
  4.      Louvers and Exhaust
Purpose: Water Treatment Facility and Electrical Building Addition
JDS/jds3_1510775874.jpg

JDS Mining - Mount Polley

2014

JDS Mining - Mount Polley

Custom Steel Building57' x 240' with 56' eaves w/Lean To
  1. Design and Install
  2. Fully Lined with Insulation
  3. All doors and Ventialtion
  4. 10 Ton Radio Controlled Overhead Crane
  5. Lean To coomplete with framed and finished office space
Purpose: Magnetite Processing Plant