Drive Replacement

Our Structural team cut in and framed in new roof hatches so that our mechanical team could remove an old drive from a Bucket Elevator. After the hatch was framed in our team re roofed and trimmed the top of this elevator. Our Mechanical team ordered a new custom built gearbox from the USA to  replace this drive. We will also replace the head pulley lagging, bushings and non drive side bearing. New drive is scheduled to be installed in April of 2021. Its nice to see the two sides of our company working together on the same project. There are some good synergies between our structural and mechanical division.

Have a question or need more information about our industrial services? Contact us today.