New seed cleaner feed drag conveyor on a galvanized support structure inside the Cargill Camrose canola crush plant

Capital projects and shutdowns · Camrose, AB · 2024–2026

Conveyor replacements and annual shutdowns at Cargill's Camrose canola crush plant

The client

Cargill's canola crush plant in Camrose, Alberta runs around the clock, so mechanical work has to fit inside short, planned outages. Pacific Apex returns to the plant year after year for its annual shutdown and for complex capital projects, from planning and engineering through fabrication, installation and commissioning.

2026: Seed cleaner feed drag conveyor replacement

The plant's seed cleaner feed drag conveyor, five floors up inside the process building, needed to be replaced with a new bulk-flow drag conveyor during the August 2026 shutdown.

  • Project management and detailed shutdown planning
  • Engineering coordination and stamped fabrication drawings
  • New galvanized support structure and abrasion-resistant feed and discharge chutes, fabricated in advance
  • Engineered rigging plan and lifting attachments
  • About 15,500 lb of conveyor components hoisted from the second to the fifth floor through the operating plant and staged before the outage
  • Removal of the old conveyor, supports, drive and chutes
  • Installation and alignment of the new conveyor, drive package and chutes, with modifications to the existing aspiration hood and lines
  • Mechanical commissioning, startup support and turnover

All removal, installation and commissioning was completed inside the planned outage window. Since startup the conveyor has run continuously at full rates.

2025: Splitting a 200-foot drag conveyor in two

The pelletizing feed drag, an en-masse conveyor nearly 200 feet long, was too long for its chain to carry the torque it needed. Pacific Apex split it into two shorter conveyors of about 100 feet each, with the first discharging directly into the second, so each chain runs well within its rating.

  • New head and tail sections, drive and gearbox on a new torque-arm support frame
  • Existing trunking reused where possible, keeping the same overall length in the process
  • Stamped lift plan, engineered lifting beam and temporary supports hung from the plant bridge
  • Safe work procedures for every critical lift and hot-work task, reviewed with the crews and Cargill engineering
  • Completed in a 7-day continuous shutdown with 20 millwrights, incident-free

Annual shutdowns

Alongside these projects, Pacific Apex supplies around 20 to 25 millwrights and welders for the plant's annual shutdown, working through preventive maintenance, corrective repairs and component rebuilds, including drag chain and sprocket replacements.

Photo gallery

Annual shutdowns, 2023 and 2024

During the plant's 2023 and 2024 shutdowns our crews rigged and replaced gearboxes, screw conveyor shafts and drag conveyor sprockets, and laser aligned the drives before start-up.