Steel frame of the BC Hydro Site C maintenance shop at sunset, Fort St. John, BC

Pre-engineered steel building · Fort St. John, BC · 2016

Maintenance shop for the BC Hydro Site C project

The project

The Site C Clean Energy Project on the Peace River near Fort St. John is one of the largest infrastructure builds in BC history. Heavy equipment on a job that size needs a large, serviceable shop on site. Pacific Apex was brought in by the contractor to erect a 120' x 250' rigid-frame steel maintenance shop with a 20-ton overhead crane.

The building

  • 120' wide x 250' long clear-span rigid steel frames, ten 25' bays
  • 42'6" eave height for large equipment and the overhead crane
  • Crane runway brackets and a 20-ton overhead crane, installed and aligned
  • Ten overhead doors, including eight 22' x 20' equipment doors
  • R20 insulated envelope with a standing seam roof, PBR wall panels and snow stops
  • Mezzanine framing inside the shop
  • Designed for a 2.80 kPa ground snow load to the BC Building Code

Building through a northern winter

Erection ran through cold weather in northeastern BC. Our crews set the rigid frames with cranes, installed the secondary steel and the insulated envelope, and worked within the site's strict safety program alongside many other contractors.

Photo gallery